dangqianzhengzhiyujilailinzhiji,jidonggaosudierbiaoduanweibaozhanggongchengdeshunlishigong,jishizhidingleyujilumiangongchengshigongfangan,xianchangshigongrenyuandingzhejiabanjiadian,qiangshijian、趕進度,力爭將雨季造成的延誤損失降至最低。截至目前,第二標段二灰土底基層已完成53%,水穩基層已完成32%,大粒徑透水基層、AC-20C下麵層試驗段已順利完成。