德(de)商(shang)高(gao)速(su)第(di)三(san)標(biao)段(duan)於(yu)五(wu)月(yue)初(chu)完(wan)成(cheng)中(zhong)麵(mian)層(ceng)施(shi)工(gong)後(hou),項(xiang)目(mu)部(bu)果(guo)斷(duan)抓(zhua)住(zhu)有(you)利(li)時(shi)機(ji),開(kai)展(zhan)了(le)一(yi)係(xi)列(lie)施(shi)工(gong)目(mu)標(biao)管(guan)理(li)工(gong)作(zuo),推(tui)進(jin)施(shi)工(gong)進(jin)度(du)。通(tong)過(guo)嚴(yan)格(ge)目(mu)標(biao)管(guan)理(li),設(she)定(ding)施(shi)工(gong)目(mu)標(biao),合(he)理(li)控(kong)製(zhi)各(ge)工(gong)序(xu)施(shi)工(gong),該(gai)標(biao)段(duan)工(gong)程(cheng)進(jin)度(du)明(ming)顯(xian)提(ti)高(gao),現(xian)已(yi)完(wan)成(cheng)上(shang)麵(mian)層(ceng)試(shi)驗(yan)段(duan)施(shi)工(gong),將(jiang)於(yu)5月21日正式開始上麵層施工,預計6月8日完成三標段所有上麵層施工及防護與邊坡工程施工工序。